Jun.25.2020
         

German LNG project selects Spanish-German venture for EPC tender process

German LNG project selects Spanish-German venture for EPC tender process

German LNG Terminal, the developer of the import project in Brunsbuettel, has selected a Spanish-German partnership as an exclusive candidate for the final phase of its EPC tender procedure.

Image: German LNG Terminal

The partnership consists of Spain’s Cobra Instalaciones y Servicios, Sener, and Germany’s TGE Gas Engineering.

This final phase will consist of a “comprehensive value-improvement exercise and a detailed price actualization” to make the LNG project more cost efficient.

The German LNG project, owned by Dutch Gasunie and Vopak, and Germany’s Oiltanking, plans to sign a binding EPC contract by the end of 2020.

Following the final deal, work would start on detailed design and engineering, necessary to develop purchase orders of long-lead items.

The LNG project started international prequalification process to select EPC contractor back in June 2019 announcing a shortlist in October the same year.

The contract scope includes a jetty with two berths, with both unloading and loading capabilities, for LNG carriers ranging from 1,000 up to 265,000-cbm.

The terminal will have storage tanks and LNG regasification and distribution facilities for a total capacity up to 8 bcm per year.

The project developer says it is also in the process of completing the permit application for the planning of the port infrastructure, including the waterside facilities.
The post German LNG project selects Spanish-German venture for EPC tender process appeared first on Offshore Energy.