LNG Plant Engineering

 

 

LNG Plant Moab Utah

Southwest USA

CONCEPT: Cost-effective LNG using robust liquefaction process

OVERVIEW: The Lisbon Group provided the project framing, LNG Technology, construction management, start-up commissioning and early operations support. Then we provided the full process package using our propriety refrigeration system, led start-up and commissioning, and handed over of operations for the Lisbon Valley LNG plant. The plant has achieved greater than 93% availability and operated with zero LTIs. We currently continue to serve as external engineering resources to ensure the facility meets production targets.

HIGHLIGHTS:

  • 22, 000 gal / day; 93% Availability; Zero LTI
  • 12 month project life cycle; 90 days construction
  • Upgradable to 100,000 gal / day

MARKETS SERVED: The facility started operations in 2008, and since then has reliably served the industrial, frack, remote power generation, and transportation markets within the Southwest United States.